Renovations · Sep 2026

Renovations &
Your Automated Gate

Widening the opening, moving the pillars, re-using the motor: what a renovation changes about your automation, and the order to do it in.

Renovations treat the automated gate as furniture: shift the wall, widen the driveway, pour the new paving, and drop the gate back in at the end. In practice the gate and its automation are an engineered system tied to the geometry of the opening, and every metre you add or move changes what the motor is being asked to do. Handled in the right order, a relocation is a routine part of the build. Handled in the wrong order, it becomes the jackhammered-and-redone part of the build.

To be clear about scope: our retrofit guide covers adding a motor to a gate that has never had one, and our installation mistakes guide covers fault-spotting on a finished job. This article is for the renovation itself — what moving or enlarging the opening does to the automation, and the sequence that keeps it painless.

Geometry Decides Before Budget Does

A gate motor is sized to the gate's weight and its wind area, and both grow with a widening in a way that catches people out. Lengthening a sliding leaf adds weight along its whole run and adds sail area the motor fights on every windy Highveld afternoon; doubling a driveway opening often doubles the load rather than nudging it. Before promising that the existing motor will be re-used, have the new opening measured and the motor re-specified against our sizing guide. The honest answer is sometimes "the motor moves across", and sometimes it is "the motor was borderline before and this pushes it into the next class".

Sliding or Swing Changes the Answer

The gate type decides what "wider" physically costs. A sliding gate needs clear track run equal to the leaf width plus a parking space alongside the opening — widening it eats driveway length that may simply not exist. A pair of swing leaves needs an arc clear of the wall, the slope and the pavement, and on a busier road a wide swing arc is a genuine access problem. If the renovation is the moment the gate type itself is being reconsidered, our sliding versus swing comparison is the place to settle it, before pillars are cast rather than after.

Moving Pillars Means Concrete and Services

New pillar positions mean new foundations, and foundations run on calendar time the same as any new install — the staged wait in our concrete curing guide applies to relocated plinths exactly as it does to fresh ones. Renovations add two complications. First, services: the old pillar may be carrying the intercom conduit, electric fence wiring or the motor supply cable, and every one of those needs a planned route to the new position. Second, approvals: a boundary wall or gate on the street boundary can involve municipal sign-off, which our council approval guide explains, and that paperwork takes weeks nobody budgeted for.

What Happens to the Existing Motor

Sequencing the Build

Build stageWhat the gate and automation need
DesignNew opening measured; motor re-specified; sliding run or swing arc confirmed; approvals lodged
DemolitionPower isolated and locked off; motor, control box and cabling protected or removed; pillars demolished last
CivilsNew plinths cast and conduits laid for motor supply, intercom and beams — before any slab or paving goes down
Walls and pillarsPillars built plumb and to size with conduit stubs in the right places; curing time respected
Gate installationGate hung and rack aligned first; motor mounted and coupled only once the leaf runs freely by hand
CommissioningBeams aligned and tested, forces and limits set, handover documents and warranty filed

The one-line version: conduits and plinths before concrete and paving, gate before motor, settings after everything. The renovation programme is the automation programme — the installer needs to be in the builder's schedule, not summoned after it.

The classic false economy. Re-using an undersized motor on a wider gate, and skipping the conduits because "the cable can just go under the paving". The first shows up as a motor that struggles on windy days for the next ten years; the second shows up the first time that cable faults, and the answer is a freshly jackhammered driveway.

Frequently Asked Questions

Can my existing motor run a wider gate?

Only if it is re-specified against the new weight and wind area. A widening often pushes a borderline motor into the next size class, and the honest assessment costs less than a motor that struggles for a decade.

Do I need approval to move a boundary wall or gate?

Often yes, particularly where the wall sits on the street boundary or the scheme has aesthetic rules. Check the municipal and scheme requirements at design stage — the paperwork moves slower than the builder does.

How long must a new plinth cure before the motor goes on?

The same staged timeline as any new installation: roughly a week before a light residential motor is mounted and run gently, longer for heavy gates. The curing guide sets out the stages and the SA weather caveats.

Can the beams and settings just be moved across?

No. A relocated installation is re-commissioned: beams re-aimed for the new opening, force and limit settings re-taught, and the safety functions tested before the gate returns to daily use.

A renovation is the one moment when the gate can be made wider, quieter, faster and better protected for a fraction of what it would cost as a separate project later — but only if the automation is in the plan before the concrete is. Bring the gate into the design conversation early, and the new driveway will open the way it should. If you are planning changes to an entrance and want the automation spec'd around the build, that is a site visit worth booking.

Renovating Your Entrance?

We spec, move and re-commission the automation around your build — across Pretoria and Centurion.

📞 Call 072 079 7084 Get Free Quote Online
💬